NTPC proposes to expand the capacity of its existing Simhadri Thermal Power Project (Simhadri TPP, 2x500 MW), by adding 1000 MW capacity in Stage-II.
Feasibility report for Simhadri TPP, Stage-II (2x500 MW) has been finalized with an estimated cost of the project as Rs.4844.40 Crores (At 3rd Qtr. 2006 price level). Various input tie-ups and clearances including environment clearance from Ministry of Environment & Forests are being processed.
Subject to timely clearances/approvals both 500 MW units of the project are envisaged for commissioning in 11th Plan period. Additional average daily power generation from Simhadri Stage-II (2x500 MW) after Commercial Operation Date (COD) will be 19.2 Mega Units (MUs) at 80% Plant Load Factor (PLF) and 21.6 MUs at 90% PLF.
This information was given by the Power Minister Shri Sushilkumar Shinde in a written reply to a question in the Lok Sabha today.