Dilip Buildcon Ltd has announced that the project "Four Laning from km 308.550 to km 358.500, Byrapura to Challakere section of NH-150 A, on Hybrid Annuity Mode under Bharatmala Pariyojna in the state of Karnataka Pkg - II, has been provisionally completed. The Provisional completion certificate has been issued by the authority and had declared the project fit for entry into commercial operation as on December 15, 2020 and consequently the company is entitled to receive the bonus of Rs 8.84 crores in lieu of early completion (i.e. 105 days prior to the revised scheduled completion date) of the said Project.
Shares of Dilip Buildcon Ltd was last trading in BSE at Rs.394.9 as compared to the previous close of Rs. 392.45. The total number of shares traded during the day was 3965 in over 147 trades.
The stock hit an intraday high of Rs. 396.9 and intraday low of 393.2. The net turnover during the day was Rs. 1564723.